 | Loading… |
|
18 | 27 | 28 | 29 | 30 | 1 | 2 | 3 |
19 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
20 | 11 | 12 | 13 | 14 | 15 | 16 | 17 |
21 | 18 | 19 | 20 | 21 | 22 | 23 | 24 |
22 | 25 | 26 | 27 | 28 | 29 | 30 | 31 |
23 | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|
Jan | Feb | Mar | Apr |
May | Jun | Jul | Aug |
Sep | Oct | Nov | Dec |
|
|
|
|  |
|
 | Loading… |
|
18 | 27 | 28 | 29 | 30 | 1 | 2 | 3 |
19 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
20 | 11 | 12 | 13 | 14 | 15 | 16 | 17 |
21 | 18 | 19 | 20 | 21 | 22 | 23 | 24 |
22 | 25 | 26 | 27 | 28 | 29 | 30 | 31 |
23 | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|
Jan | Feb | Mar | Apr |
May | Jun | Jul | Aug |
Sep | Oct | Nov | Dec |
|
|
|
|  |
| | | | |
| 16476142 | 6 | APPROVE | 5/1/2012 | 5/1/2012 | Special Request | BS | notification to make correction on destination of pipeline. Desitination should be SS208F-pump instead of SS208F | |
| 16509234 | 6 | APPROVE | 4/23/2013 | 4/15/2013 | ROW Assignment | MM | ROW Assignment from Black Elk Energy, LLC (3033) to Renaissance Offshore, LLC (3209) | |
| 16396222 | 6 | APPROVE | 9/3/2009 | 9/1/2009 | Departure/Alternate Compliance Request | SK | Request to that all newly laid sections of pipeline, tie-in spools, and riser will be hydrostatically tested for 8 hours in the field and then perform a two hour leak tested of the entire pipeline in lieu of 30 CFR 250.1003(b)(1) hydrotest requirement. | |
| 16385478 | 6 | APPROVE | 7/22/2009 | 5/21/2009 | ROW Modification | SK | Request to Modify Right-of-Way grant OCS-G 13496 and associated pipeline Segment No. 6 by 1) Partially Decommission by removal 1859 feet of damaged pipe (Segment No. 16198) displaced by Hurricane Ike; 2) Replacing damaged pipe with 1752 feet of new pipe to reconnect to Platform F, all located in Ship Shoal Area Block 208. | |
| 16385527 | 6 | APPROVE | 8/11/2010 | 9/30/2009 | Modification Completion Report | SK | Request to Modify Right-of-Way grant OCS-G 13496 and associated pipeline Segment No. 6 by 1) Partially Decommission by removal 1859 feet of damaged pipe (Segment No. 16198) displaced by Hurricane Ike; 2) Replacing damaged pipe with 1752 feet of new pipe to reconnect to Platform F, all located in Ship Shoal Area Block 208. | |
| 316187727 | 6 | ACCEPTED | 3/28/2023 | 2/20/2023 | Annual Cathodic Protection Report | AE | 2022 Calendar Year Cathodic Protection Report. | |
| 407193571 | 6 | ACCEPTED | 8/27/2024 | 2/29/2024 | Annual Cathodic Protection Report | AD | 2023 Calendar Year Cathodic Protection Report. | |
| 24533024 | 6 | APPROVE | 8/17/2020 | 7/15/2020 | ROW Modification | MM | Request Cessation of Operations for ROW OCS G13946, PSN 6 | |
| 24319752 | 6 | ACKNOWLEDGED | 6/29/2020 | 6/25/2020 | Out of Service Notification | AE | 60-Day Notification PSN 6 - Out-of-Service | |
| 219532653 | 6 | ACKNOWLEDGED | 5/12/2021 | 5/11/2021 | Return to Service Notification | AE | Return to Service | |
| 543063904 | 6 | REVIEW | 5/6/2025 | 2/12/2025 | Annual Cathodic Protection Report | AD | 2024 CY Cathodic Protection Report.
PSN 15172 reading is -.897 and PSN 15749 reading is -.937. | |
| 16204915 | 7 | APPROVE | 8/25/2004 | 8/24/2004 | Departure/Alternate Compliance Request | TL | Requests a departure from the NTL 98-20, Section IV B (1), on site requirements requiring safe working areas to be marked with buoys while moving the Ensco 93 jack-up rig over South Marsh Island Block 49 "A", Well A-4. | |
| 16230674 | 7 | CANCELLED | 5/3/2012 | 4/29/2005 | Departure/Alternate Compliance Request | TL | Requests a departure from 30 CFR.250.1007(a)(5) and NTL 98-20 Section III,(C.2d) for pipeline pre-installation surveys and requests approval to utilize the existing survey data in lieu of a centerline survey for the proposed Right-of-Way pipeline to be submitted originating at "F" platform to "B" platform all located in West Delta Block 133. | |
| 16260009 | 8 | CANCELLED | 5/15/2012 | 1/11/2006 | Departure/Alternate Compliance Request | TL | Requests a waiver to use 3D seismic to produce the Hazards and Site-specific report for four proposed wells in Garden Banks Block 258, Lease OCS-27632. | |
| 15925416 | 9 | APPROVE | 3/15/2001 | 3/15/2001 | ROW Modification | MB | Change of service from gas/condensate to bulk gas. | |
| 16070410 | 9 | APPROVE | 3/15/2001 | 3/12/2001 | ROW Modification | MB | Change from unidirectional to bidirectional. | |
| 16488287 | 9 | APPROVE | 9/20/2012 | 9/20/2012 | Departure/Alternate Compliance Request | BH | Request for time extension until August 30, 2013 to decommission the pipeline due to potential future utility based on recent lease sale. | |
| 16486630 | 9 | APPROVE | 10/29/2012 | 8/24/2012 | Departure/Alternate Compliance Request | DG | Request departure from 30 CFR 250.1006 from flush and fill until March 30, 2013 | |
| 16504880 | 9 | APPROVE | 3/13/2013 | 3/13/2013 | Special Request | BS | RESCIND ROW RELINQUISHMENT APPROVED ON 3/9/2012 and expire the right of way to both ROW title holders - Chevron and McMoRan | |
| 16512865 | 9 | APPROVE | 5/31/2013 | 5/15/2013 | ROW Relinquishment and Decommissioning Application | LC | Relinquish ROW OCS G13439 in its entirety and decommission pipeline in-place. | |